Key findings

  • The most credible outlook is a selective construction expansion, not a uniform boom. Social and affordable housing, infrastructure and enabling works have stronger medium-term support than speculative private development.
  • The latest data do not show a broad-based recovery in new work: private housing weakened in July 2026 while infrastructure activity was comparatively more resilient. This makes composition, rather than the construction headline, crucial.
  • Planning reform can improve the supply of developable opportunities, but it cannot by itself resolve viability, utility capacity, procurement sequencing or shortages in specialist occupations.
  • The infrastructure pipeline and long-term affordable-housing settlement create a substantial potential workload. They also concentrate demand for overlapping skills, professional services and local supply-chain capacity.
  • The practical opportunity lies in converting mature programmes into deliverable packages: servicing sites, coordinating dependencies, aggregating demand, developing suppliers and retaining the workforce needed for repeat delivery.

Thesis: the next upswing is more likely to be delivery-constrained than permission-constrained

**Forecast horizon: September 2026 to September 2029.** Sanctuary’s central judgement is that UK construction is entering an uneven expansion in which the limiting factor will increasingly be the ability to deliver, rather than the absence of policy ambition or prospective demand. Publicly supported social and affordable housing, enabling infrastructure, energy, transport and resilience schemes offer the clearest medium-term floor. Private housebuilding should recover later and less consistently because a consented scheme still depends on mortgage affordability, sales rates, build-cost confidence and developer appetite.

The short-term evidence does not yet support the idea of a broad private-development rebound. Great Britain construction output fell by 0.5% in the three months to July 2026, with new work down 0.4%. Private housing new work fell by 4.9% in July, whereas infrastructure new work had risen by 1.9% in the second quarter. July is one monthly observation and should not be over-read, but the pattern is consistent with a market in which programmed infrastructure is holding up better than private residential starts. Office for National Statistics (2026) Office for National Statistics (2026)

Construction output prices were 1.9% higher year on year in June 2026. That is a calmer backdrop than the severe cost shocks earlier in the decade, but it does not eliminate project-level risk: specialist-package availability, design maturity, financing and programme delay can still overwhelm modest aggregate price growth. Office for National Statistics (2026)

The distinction matters for councils, developers, housing providers and contractors. A place can have a high housing target and a long list of allocated sites without having a near-term construction market. Output follows a conversion chain: land and planning certainty, viable funding, utility and access works, procurement, mobilisation, starts and completion. Failure at any link can hold back the whole programme. The strongest commercial and local-economic opportunity is therefore in organisations able to reduce these hand-off failures, not simply in those waiting for aggregate housebuilding volumes to rise.

A larger pipeline improves visibility, but not every listed project is a work package

The demand case has strengthened. The Spending Review committed £39 billion over ten years to the Social and Affordable Homes Programme from 2026-27, with annual spending reaching £4 billion in 2029-30. It also set out £4.8 billion of financial transactions for housebuilding between 2026-27 and 2029-30, alongside land remediation and enabling-infrastructure investment. HM Treasury (2025) Subsequent programme announcements placed greater emphasis on council housebuilding and devolution, improving the prospect of locally anchored delivery partnerships where allocations become operational. Ministry of Housing, Communities and Local Government (2026)

Infrastructure is similarly material. The 2026 Infrastructure Pipeline identified 734 planned projects and £718 billion of public and private investment over the coming decade. National Infrastructure and Service Transformation Authority (2026) The 10 Year Infrastructure Strategy is intended to replace historically uneven investment and weak coordination with a more stable framework for planning and supply-chain investment. HM Treasury and National Infrastructure and Service Transformation Authority (2025)

Yet a pipeline is not a forecast of work starting tomorrow. It includes projects at different stages of development, and prospective investment is not equivalent to a funded contract. Treating all announced capital as immediate addressable demand leads firms to over-hire, over-bid or carry excessive bid costs. Conversely, dismissing the pipeline because some projects will be delayed misses its real value: it gives clients, providers and suppliers a basis to identify where repeatable demand may emerge and what capability must be developed in advance.

Housing and infrastructure programmes also compete as well as reinforce one another. Growth locations require enabling works and network capacity at broadly the same time as homes are expected to be delivered. They may draw on the same civil engineering firms, groundworkers, electrical specialists, planners, surveyors and project managers. A smaller scheme with secure land, a funded infrastructure sequence and an agreed procurement route can therefore be a better opportunity than a much larger allocation still dependent on unresolved connections or approvals.

**Sanctuary recommendation.** Assess opportunities through five maturity gates: policy and land certainty; viability and funding; enabling infrastructure; procurement and delivery model; and workforce and supplier readiness. The first gates establish potential. The latter two determine whether potential becomes a credible work package and local economic value.

Housing recovery is plausible, but policy targets should not be mistaken for delivery forecasts

The Office for Budget Responsibility’s November 2025 central forecast expects net additions to the UK housing stock to fall to 215,000 in 2026-27 before rising to 305,000 in 2029-30. It also forecasts residential investment growth of around 7% in both 2027 and 2028, while expecting average mortgage rates to move towards 5% by 2029. Office for Budget Responsibility (2025) This supports a delayed-recovery thesis rather than an immediate housebuilding surge.

The timing assumption is important. Earlier OBR analysis estimated that planning-policy changes would add 170,000 net housing additions over its five-year forecast period, with most of the effect arriving from 2027-28. Its reasoning was straightforward: local plans, site preparation, development capacity and construction do not adjust instantly. Office for Budget Responsibility (2025) The Planning and Infrastructure Act and the subsequent infrastructure-planning implementation plan may reduce parts of that delay, but their eventual effect still depends on implementation, local decisions and individual projects progressing through delivery. Ministry of Housing, Communities and Local Government (2025) Ministry of Housing, Communities and Local Government (2026)

This is a useful corrective to claims that England’s housing ambition can be read directly into future construction output. The OBR projects 1.49 million UK-wide net additions between 2024-25 and 2029-30. That measure is close in scale to the stated policy ambition, but it is not England-only gross housebuilding: net additions and new-build completions are different measures. Office for Budget Responsibility (2025) Conflating them overstates certainty and obscures the contribution of conversions, demolitions and the rest of the UK.

The counterargument is that weaker private housebuilding may free labour and contractor capacity for affordable housing. There is some local truth in this. However, capacity is not interchangeable: a housing slowdown does not automatically provide the civils, electrical, utility, design-management or regulatory capability required for major infrastructure and complex regeneration. The more likely outcome is selective redeployment, with shortages persisting in particular occupations and geographies.

For firms, the implication is to prepare for the pre-construction window. Land promotion, surveys, remediation, utilities coordination, design, programme controls and procurement may grow before brick-and-block volumes become evident in national data. SMEs that develop evidence of capability in two or three repeatable packages may be better placed than firms that pursue every headline opportunity without the working capital, systems or labour to deliver it.

The binding constraint is coordinated capability: people, suppliers and management capacity

The scale of prospective investment makes workforce planning a core delivery issue rather than a corporate-social-responsibility add-on. NISTA estimates that delivering projects in the 2026 Infrastructure Pipeline will require an average annual construction and infrastructure workforce of 629,000 to 706,000 over the next five years. National Infrastructure and Service Transformation Authority (2026) The Government’s consultation on Industry Training Board reform also recorded around 28,000 seasonally adjusted construction vacancies in the three months to January 2026. Department for Education (2026) Vacancies are not a complete estimate of the skills gap, but they are a warning against assuming labour can expand without friction.

The risk is not simply a national shortage of workers. It is a mismatch in timing, place and specialism. A funded scheme may still stall because it cannot secure site managers, estimators, planners, civils trades, electrical capability or a viable specialist subcontract package at the required time. That pressure can raise tender prices, push risk down fragile supply chains and produce labour churn between programmes. Stable aggregate construction-price inflation does not prevent these delivery failures.

This has direct implications for local economic value. A pipeline can create better employment and entrepreneurship outcomes only if local people and firms can access real, sustained work. One-off training that is disconnected from forthcoming packages will not build durable careers or productive businesses. Equally, large clients cannot expect smaller suppliers to invest in skills, accreditation, digital systems or plant if procurement is fragmented and future work remains opaque.

**Sanctuary recommendation.** Major clients and place leaders should run a quarterly delivery-capacity review alongside their financial business case. It should identify critical occupations, constrained subcontract packages, expected procurement dates, site dependencies, local supplier capacity and named mitigation owners. Publishing a credible forward pipeline, coordinating procurement calendars and using longer, repeatable commitments can give SMEs a firmer basis to recruit, collaborate and invest. This is management capability applied to programme certainty—not a substitute for it.

Scenario view: what would change the outlook between now and autumn 2029?

**Base case: selective expansion, increasingly visible from 2027-28.** Affordable-housing allocations, public capital programmes and infrastructure procurement progressively lift demand. Private housing improves, but unevenly, and output remains constrained by the pace at which sites become serviced, financeable and staffed. This is consistent with the OBR’s later-period rise in housing additions and residential investment, while respecting the weak near-term private-housing signal. Office for Budget Responsibility (2025) Office for Budget Responsibility (2025) Office for National Statistics (2026)

**Upside case: coordinated delivery creates a stronger 2028-29 upswing.** Housing providers translate longer-term funding into repeat programmes; remediation and enabling works unlock priority sites; infrastructure projects move from development into procurement; and suppliers see sufficient continuity to invest in people and plant. The benefit would not merely be higher output. It would be more predictable work, better conditions for SME growth and less wasteful stop-start mobilisation.

**Downside case: an announced pipeline does not become a buildable pipeline.** Private schemes remain unviable or slow to sell; implementation of planning changes takes longer than assumed; enabling dependencies postpone starts; public programmes face affordability or procurement bottlenecks; and specialist labour competition erodes delivery certainty. In this case, pockets of infrastructure activity would persist, but the housing response would disappoint.

These are conditional scenarios, not probability-weighted predictions. The base case is stronger than it was before the affordable-housing settlement and fuller infrastructure pipeline, but it remains vulnerable because the latest output and new-work data do not yet show a broad construction recovery. HM Treasury (2025) National Infrastructure and Service Transformation Authority (2026)

What decision-makers should watch—and do

The most useful indicators over the next 6 to 18 months are conversion indicators, not announcements alone: affordable-housing allocations becoming land deals, tenders and starts; infrastructure projects moving into procurement and construction; the composition of quarterly new orders; and evidence that constrained occupations and specialist packages can be secured. Ministry of Housing, Communities and Local Government (2026) Office for National Statistics (2026) National Infrastructure and Service Transformation Authority (2025) National Infrastructure and Service Transformation Authority (2026)

The base case should be reconsidered if housing and infrastructure new orders fall persistently through 2027, public starts are repeatedly deferred, development viability deteriorates materially, or priority sites remain blocked by enabling dependencies. The July decline in private housing new work is an early warning, not sufficient evidence on its own to invalidate the outlook. Office for National Statistics (2026)

For councils, delivery bodies, developers and local firms, the central task is to build live delivery intelligence: a register of mature schemes, dependency maps, a procurement timetable, a supplier-development plan and workforce routes tied to actual packages of work. The opportunity is real, but it will accrue disproportionately to places and organisations that can turn policy, funding and pipeline visibility into disciplined delivery.

Sanctuary delivery-conversion framework: from policy ambition to construction outputOriginal Sanctuary analytical framework. It is a conceptual delivery sequence, not a numerical model.
Policy target and funding envelope
Land, plan and consent certainty
Utilities, remediation and enabling infrastructure
Viability, procurement and risk allocation
Workforce and SME supply-chain capacity
Starts, completions and local economic value

Research foundation

References

  1. Office for National Statistics (2026). Construction output in Great Britain: July 2026. Office for National Statistics statistical bulletin.
    Source ↗
  2. Office for National Statistics (2026). Construction output in Great Britain: June 2026, new orders and Construction Output Price Indices, April to June 2026. Office for National Statistics statistical bulletin.
    Source ↗
  3. HM Treasury (2025). Spending Review 2025. HM Treasury.
    Source ↗
  4. Ministry of Housing, Communities and Local Government (2026). The Social and Affordable Homes Programme and the reinvigoration of council housebuilding. GOV.UK.
    Source ↗
  5. National Infrastructure and Service Transformation Authority (2026). Infrastructure Pipeline update signals future workforce needs. GOV.UK.
    Source ↗
  6. HM Treasury and National Infrastructure and Service Transformation Authority (2025). UK Infrastructure: A 10 Year Strategy. GOV.UK.
    Source ↗
  7. Office for Budget Responsibility (2025). Economic and fiscal outlook – November 2025. Office for Budget Responsibility.
    Source ↗
  8. Office for Budget Responsibility (2025). Economic and fiscal outlook – March 2025. Office for Budget Responsibility.
    Source ↗
  9. Ministry of Housing, Communities and Local Government (2025). Landmark Planning and Infrastructure Bill becomes law. GOV.UK.
    Source ↗
  10. Ministry of Housing, Communities and Local Government (2026). Streamlining infrastructure planning: implementation plan. GOV.UK.
    Source ↗
  11. Department for Education (2026). Industry Training Board reform. GOV.UK consultation.
    Source ↗
  12. National Infrastructure and Service Transformation Authority (2025). UK Infrastructure Pipeline. GOV.UK.
    Source ↗
  13. Peter Facey. Hero image: Itchen Farm Park and Ride site under construction - geograph.org.uk - 1221400.jpg. Wikimedia Commons · CC BY-SA 2.0.
    Image source ↗