Key findings

  • The sharp rise in contracted demand offers is evidence of competition for grid access, particularly from data-centre proposals; it is not a forecast of equivalent electricity consumption or completed investment.
  • Readiness tests and strategic-demand routes can release capacity from weak proposals, but poorly designed criteria could advantage applicants with the greatest administrative and financial resources rather than the strongest productive case.
  • A connection offer is an important milestone, not a delivery plan. Reinforcement, long-lead equipment, planning, land, construction and energy-cost exposure can still determine whether a project proceeds.
  • Lower industrial energy consumption does not automatically create usable capacity for new development: network constraints are specific to place, voltage and the timing of demand.
  • The economic return from new capacity will be stronger where sponsors, regulators and places connect power access to skills, suppliers, resilience, transport and durable local value.

Grid access is now an allocation problem

The UK’s grid-access challenge to 2030 is no longer well described as a slow-moving queue. It is an allocation problem: how should scarce, location-specific network capacity be assigned when data centres, industrial electrification, electric-vehicle charging, ports, logistics and storage are all seeking access?

The distinction matters because a connection date can shape where investment locates, whether it can be financed and which places capture jobs and supply-chain activity. Yet a queue position is a weak proxy for whether a project will use power productively. The more relevant question is whether demand is deliverable: linked to a credible operational need, a viable site, finance, a network solution, equipment, permissions and a route to construction.

Ofgem reports that contracted demand offers rose from 41GW in November 2024 to 125GW in June 2025. Data-centre proposals accounted for at least 80GW of that increase. In response, Ofgem is pursuing stronger commitment requirements and milestones, including evidence of a credible end user, financial and technical capability, and progress in procuring long-lead electrical equipment (Ofgem, 2026) ↗.

These figures demonstrate intense commercial interest; they do not forecast metered demand. An offer does not establish that a sponsor will obtain finance, construct its site, be energised to schedule or operate at its requested load. Projects can be redesigned, delayed or abandoned. But that gap is precisely why allocation matters. Reservations backed by limited evidence can delay mature schemes and complicate network planning for projects that are ready to proceed.

The policy objective should therefore be more demanding than faster processing. It should be to convert access to scarce network capacity into operating assets with a credible economic purpose. That means discouraging option-holding without creating a process so expensive or complex that viable smaller businesses are excluded before their projects can mature.

Readiness can improve allocation—but it can also concentrate advantage

Government’s work on strategic demand points towards a more active approach. It considers reserving future capacity, reallocating capacity released by departing projects and giving strategic demand greater weight in network design. Potential categories include AI Growth Zones, EV charging hubs and manufacturing electrification. Importantly, the framework recognises that national economic importance does not make every proposed location technically suitable for a large connection (DESNZ, 2026) ↗.

The mechanism is persuasive in principle. Milestones make it harder to retain capacity without demonstrable progress. Where a scheme cannot evidence an end user, delivery capability or movement on critical dependencies, capacity may be reassigned rather than tied up indefinitely. Strategic designation may also enable network planning to anticipate credible demand instead of responding only after individual applications arrive.

However, reform redistributes opportunity as well as capacity. Large sponsors can more readily pay for grid studies, specialist advisers, site options and early equipment commitments. A smaller manufacturer, local developer or entrepreneur may have a productive proposal but less capacity to assemble such evidence at an early stage. If strategic criteria are opaque, the system risks replacing queueing by date with competition in administrative and financial firepower.

There is also a case against treating current readiness as the sole measure of merit. An earlier-stage project may warrant support where it is integral to industrial transition or resolves a genuine local constraint. The answer is not to preserve weak reservations indefinitely. It is to apply staged and proportionate requirements: the evidence threshold should rise with requested capacity, network impact and proximity to energisation.

**Sanctuary recommendation.** Ofgem and government should publish clear qualification rules, milestones and reasons for approval, refusal and delay. Strategic status should demonstrate a route to energisation and economic use, rather than simply membership of a favoured sector. A transparent route for smaller projects is necessary if the system is to identify productive demand beyond the largest applicants.

An offer to connect is not a plan to deliver

Connections reform can make allocation more disciplined, but it cannot manufacture transformers, switchgear, construction labour, planning consent, land rights or local acceptance. For investors, the decisive period through 2030 is likely to be the interval between receiving an offer and operating an energised site.

The wider policy setting acknowledges these interdependencies. The Clean Energy Industries Sector Plan treats electricity networks, ports, rail and road as connected requirements for industrial growth. Ofgem’s RIIO-3 electricity-transmission determinations provide part of the regulatory and investment framework for network expansion (DESNZ, 2025; Ofgem, 2025) ↗ ↗. These are important enabling conditions, but they do not guarantee that an individual sponsor will connect at its preferred date or cost.

A serious power-readiness assessment should therefore look beyond a headline connection date. It should identify the reinforcement and customer works required; responsibility for long-lead equipment; land-control and planning status; construction access; and whether cost escalation or delay would undermine the business case. It should also test whether demand can be phased, shifted or curtailed without compromising the operation. A failure in any one dependency can make an apparently secured connection commercially unusable.

Operating economics add a further constraint. The UK Steel Strategy sets out measures intended to improve electricity-cost conditions for eligible energy-intensive firms, including existing support, network-charge changes and a proposed British Industrial Competitiveness Scheme. These are targeted interventions, not a universal industrial electricity price (Department for Business and Trade, 2026) ↗. ONS indicators for May 2026 recorded a monthly average System Average Price of gas 42% above the previous year and an electricity system price 49% higher year on year. These are system-level measures rather than a project’s contracted energy bill, but they underline the need for explicit procurement, hedging and resilience plans (ONS, 2026) ↗.

Flexibility, storage, on-site generation and phased energisation can improve some business cases. They are not universal remedies: their value depends on local constraints, tariffs, interruption costs and the user’s ability to alter operations. Credible demand is not necessarily the demand seeking the smallest connection. It is demand whose infrastructure and economics remain viable under realistic delivery conditions.

Falling consumption is not the same as available capacity

It is tempting to infer that lower industrial energy use has freed capacity for growth. That conflates annual consumption with usable network access—and can mistake industrial contraction for infrastructure progress.

UK industrial energy consumption fell by 4.9% between 2024 and 2025, to 17.3 million tonnes of oil equivalent. DESNZ links lower energy use in iron and steel partly to steelworks closures (DESNZ, 2026) ↗. This is important context for industrial policy, but it does not establish that a new user can connect at the required substation, voltage level and time of day, or without further works.

Consumption data measures energy used over a period. Connection constraints concern whether a particular location can safely and reliably accommodate a particular demand profile. Reduced demand from a former industrial site may ease a local constraint in some circumstances, but there is no automatic mechanism by which a fall in aggregate consumption becomes suitable, affordable capacity for a different project.

**Sanctuary interpretation.** Capacity associated with lost output, jobs or productive capability should not be presented as equivalent to capacity created through reinforcement, flexibility and planned demand. The former may create a temporary local opportunity; the latter is a durable improvement in a place’s capacity to support growth. This distinction should remain explicit when energy data is used to support claims about regeneration.

Local value should sit alongside national strategic value

The distributional question is not only which sectors receive power, but which places retain the benefits. A nationally significant high-load facility may generate limited local economic value if it has weak links to workforce development, local suppliers, transport or durable employment. Conversely, a smaller industrial, logistics or charging project can have an outsized local effect when it anchors a cluster of firms or improves local productivity.

Ports illustrate the systems view required. The amended national policy statement places ports within growth, energy resilience and the energy transition, while the Clean Energy Industries Sector Plan links ports with networks, rail and road as foundations for industrial investment (Department for Transport, 2026; DESNZ, 2025) ↗ ↗. The same logic applies to industrial estates, digital campuses and logistics hubs: power is most valuable when it complements a functioning economic ecosystem rather than acting as an isolated input.

Local authorities and place partnerships should assess what a proposed user enables relative to the network capacity, land and disruption it requires. Relevant evidence includes construction logistics, transport effects, procurement plans, workforce pathways, resilience, the durability of employment and likely demand for local services and suppliers. This should inform local negotiation and planning; it should not become an informal veto over nationally necessary infrastructure.

For SMEs, much of the opportunity will be indirect. Few small firms will seek major connections, but many can participate in electrical contracting, civils, maintenance, environmental services, facilities management, training, cybersecurity, energy management and flexible-load technologies. Those gains are more likely to remain local where sponsors publish credible delivery plans and intermediary organisations help firms meet procurement, insurance, quality and cash-flow requirements.

Power access alone does not make a place economically stronger. Management capability, supplier readiness and workforce development determine whether infrastructure investment becomes repeatable local contracts, improved employability and new enterprise.

Measure energisation and productive use, not a tidier queue

The likely result of reform is selective acceleration, not frictionless abundance. Stronger commitment rules should remove some weak reservations. Strategic-demand routes may improve prospects for projects with a robust case and demonstrable readiness. Ofgem’s demand-connections reform also considers circumstances in which large demand users could take a more active role in funding or building required infrastructure, subject to network security and regulation (Ofgem, 2026) ↗.

The favourable outcome is coordinated delivery: capacity allocation, reinforcement, planning, equipment procurement and commercial development align around viable locations. The risk is a better-administered queue that clears speculative applications but still encounters bottlenecks in equipment, consents, construction capacity and site development. In that outcome, process performance improves without a commensurate increase in operating demand.

Project sponsors should treat a power-readiness dossier as a core investment document alongside the connection agreement. It should link phased load forecasts to identifiable customer demand; record land and planning status; identify reinforcement and equipment dependencies; assess flexibility and resilience options; explain the energy-cost strategy; and set out construction, workforce and local-value plans. This is not merely compliance. It makes visible the dependencies that lenders, operators and host places need to judge.

Regulators and policymakers should report outcomes alongside queue volumes: withdrawals and released capacity, revised connection dates, completed reinforcement, actual energisation and the progression of selected projects from application to operation. Ofgem reports that wider connections reform accelerated around 7.8GW of projects by an average of six years; comparable transparent reporting for demand projects would reveal more than the nominal size of the queue alone (Ofgem, 2026) ↗.

The UK can improve access for strategic demand by 2030. The harder test is whether the system converts that access into resilient, productive investment in places capable of capturing its value.

Sanctuary power-readiness framework for strategic demand projectsOriginal Sanctuary analytical framework. It is a decision checklist, not a numerical model or regulatory test.
Credible end-user demand and finance
Location, land and planning control
Connection pathway and physical reinforcement
Long-lead equipment and construction capability
Flexible operation, resilience and energy procurement
Local supply chain, skills and economic value

Research foundation

References

  1. Office of Gas and Electricity Markets (2026). Ofgem acts to free up grid capacity by tackling speculative data centre projects. Ofgem.
    Source ↗
  2. Department for Energy Security and Net Zero (2026). Accelerating electricity network connections for strategic demand. GOV.UK.
    Source ↗
  3. Department for Energy Security and Net Zero (2025). Clean Energy Industries Sector Plan. GOV.UK.
    Source ↗
  4. Office of Gas and Electricity Markets (2025). RIIO-3 Final Determinations – Electricity Transmission. Ofgem.
    Source ↗
  5. Department for Business and Trade (2026). The UK steel strategy. GOV.UK.
    Source ↗
  6. Office for National Statistics (2026). Economic activity and social change in the UK, real-time indicators: 18 June 2026. Office for National Statistics.
    Source ↗
  7. Department for Energy Security and Net Zero (2026). Energy Consumption in the UK 2026. GOV.UK.
    Source ↗
  8. Department for Transport (2026). Amended national policy statement for ports. GOV.UK.
    Source ↗
  9. Office of Gas and Electricity Markets (2026). Connect update: demand connections reform. Ofgem.
    Source ↗
  10. Pam Brophy. Hero image: Arlington Business Park - geograph.org.uk - 2251.jpg. Wikimedia Commons · CC BY-SA 2.0.
    Image source ↗

Discussion

Challenge the analysis.

No approved comments yet.